Phase 6, RW 7R-25L
The complete reconstruction of Runway 7R-25L and Taxiway A at McCarran Airport. Acme placed 397,500 square yards of 18” thick P-501 slip-form concrete paving. Three Gunert Zimmerman slip form pavers received concrete from two 400+ cy/hr Rex Model S portable batch plants. The paving was completed three weeks ahead of schedule. American Concrete Paving Association Silver National Award winner; 2010.